Work Profile Report [32W1249]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड शासन का शासनादेश संख्या 2451/।।। (2)/23-01 (प्रा.आ.)/2019, दिनांक 21.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.56
Resanction Cost :
140.56
Tentative Cost :
140.56
Exp. Upto Last Fy :
102.22
For CFY 2024-2025
Remaining :
38.34
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
102.22
Construction Started
Sanction on : 1 year 5 months ago
21 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
95 %
Tentative Completion date on : 2 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 15-Feb-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: pujargaon-bangaon pul khalati tok puliya