Work Profile Report [32W1290]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : DM Uttarkashi letter no. 43/VIII-DP-07/PWD (01)/g.yo./2023-24, dt. 27/10/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
4.00
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 1 year 3 weeks ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
95 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 05-Oct-2024