Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.25 | 3.25 | 0.000 | 3.25 | 3.250 | 2.500 |
32W1301 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Uttarakhand Govt. E File No. 64241
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.59
Resanction Cost :
97.59
Tentative Cost :
97.59
Exp. Upto Last Fy : 10.99
For CFY 2024-2025
Remaining : 86.60
Demand : 86.60
Allotment : 12.00
Exp in CFY : 10.00
Total Up to Date Exp : 20.99
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। पहाड़ कटान कार्य प्रगति पर। -- as on 24-Apr-2024