Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 1.000 | 0.000 |
32W1302 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Uttarakhand Govt. E File No. 64241
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
183.49
Resanction Cost :
183.49
Tentative Cost :
183.49
Exp. Upto Last Fy : 3.78
For CFY 2024-2025
Remaining : 179.71
Demand : 100.00
Allotment : 0.00
Exp in CFY : 0.70
Total Up to Date Exp : 4.48
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
1 year 8 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठन की कार्यवाही गतिमान। -- as on 24-Apr-2024
Physical Peramenters