Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 39.6 | 39.6 | 0.000 | 39.6 | 39.600 | 0.000 |
32W1303 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन का पत्रांक 5082/।।। (2)/2023-01 (प्रा.आ.)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 603.61 Lacs
Resanction Cost : 603.61 Lacs
Exp. Upto Last Fy : 378.59 Lacs
For CFY 2024-2025
Remaining : 225.02 Lacs
Demand : 120.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 378.59 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
6 months 1 week ago
09 Nov 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 15-Feb-2024
Physical Peramenters