Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
32W1311 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी के पत्रांक 596/तेरह (2022-23), दिनांक 04.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1.50
Resanction Cost :
1.50
Tentative Cost :
1.50
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 1.50
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 months 1 week ago
04 Oct 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 24-Apr-2024
Physical Peramenters