Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
32W275 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख्य अभियन्ता, स्तर-। का पत्र सं. 6064(1)/।। (2)/11-37 (प्रा.आ.)/2011, दिनांक 15.11.2011
TS Amount (lakhs) : 50.4 Lacs
Financial Detail
Sanction Cost : 50.40 Lacs
Resanction Cost : 50.40 Lacs
Exp. Upto Last Fy : 16.00 Lacs
For CFY 2024-2025
Remaining : 34.40 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 16.00 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
12 years 6 months ago
15 Nov 2011
Tentative Completion date:
1 year 10 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर बांटा जाना है। द्वितीय चरण का कार्य पूर्ण। -- as on 23-May-2023
Physical Peramenters