Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
32W307 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2195/(1)/।।। (2)/13-47 (प्रा.आ.)/2012, दिनांक 22.03.2013
TS Amount (lakhs) : 63 Lacs
Financial Detail
Sanction Cost : 63.00 Lacs
Resanction Cost : 63.00 Lacs
Exp. Upto Last Fy : 49.61 Lacs
For CFY 2024-2025
Remaining : 13.39 Lacs
Demand : 13.39 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 49.61 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
11 years 1 month ago
22 Mar 2013
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
वन भूमि की स्वीकृति प्राप्त। fद्वतीय चरण का कार्य पूर्ण। -- as on 19-Apr-2023
Physical Peramenters