Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
32W613 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 333/।।। (2)/14-46 (प्रा॰आ॰)/2013, दिनांक 21.01.2014
TS Amount (lakhs) : 29.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.25
Resanction Cost :
29.25
Tentative Cost :
29.25
Exp. Upto Last Fy : 3.42
For CFY 2024-2025
Remaining : 25.83
Demand : 25.83
Allotment : 0.00
Exp in CFY : 0.15
Total Up to Date Exp : 3.56
Survey work done
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
10 years 5 months ago
21 Jan 2014
Tentative Completion date:
2 years 8 months from now
31 Mar 2027
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का प्रतिकर दिया जाना शेष है। द्वितीय चरण स्टेज-। पहाड़ कटान कार्य प्रगति पर। -- as on 24-Apr-2024
Physical Peramenters