Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
32W622 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 333/।।। (2)/14-46 (प्रा॰आ॰)/2013, दिनांक 21.01.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.36
Resanction Cost :
18.36
Tentative Cost :
18.36
Exp. Upto Last Fy : 4.08
For CFY 2024-2025
Remaining : 14.28
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.08
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
10 years 5 months ago
21 Jan 2014
Tentative Completion date:
2 years 8 months from now
31 Mar 2027
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण स्वीकृत। डी.पी.आर गठित कर शासन को स्वीकृति हेतु प्रेषित। -- as on 24-Apr-2024
Physical Peramenters