Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
32W697 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी, उत्तरकाशी का पत्रांक 592/fज॰यो॰, fदनांक 28.02.2015
TS Amount (lakhs) : 2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy : 2.98
For CFY 2024-2025
Remaining : 1.02
Demand : 1.02
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.98
Work completed
Physical Progress:
At start of FY 2024-2025 : 98 %
Up to Date : 98 %
Sanction on :
9 years 4 months ago
28 Feb 2015
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 19-Apr-2023