Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 0.000 | 0.000 |
32W824 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1427/।।।(2)/ 16-02 (एम॰एल॰ ए॰) /2015दि॰ 22.03.2016
TS Amount (lakhs) : 22.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
22.30
Resanction Cost :
22.30
Tentative Cost :
22.30
Exp. Upto Last Fy : 2.66
For CFY 2024-2025
Remaining : 19.64
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.66
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
8 years 3 months ago
22 Mar 2016
Tentative Completion date:
2 years 8 months from now
31 Mar 2027
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
उक्त प्रस्ताव दिनांक 06.07.2019 को आॅनलाइन जिसका प्रस्ताव संख्या एफ.पी./यू.के./रोड़/41000/2019 है। सैद्धान्तिक स्वीकृति प्राप्त। डी.पी.आर. गठित की जा रही है। भारत सरकार के पत्र संख्या- 8बी0/यू0सी0पी0/06/32/21/एफ0सी0 दिनांक 07.09.2021 द्वारा सैद्वान्तिक स्वीकृति प्राप्त। क्षतिपूरक वृक्षारोपण एवं एन.पी.वी. की धनराशि वन विभाग के नाम जमा की जा चुकी है। नामान्तरण एवं हस्तान्तरण की कार्यवाही की जा रही है। -- as on 25-Dec-2023
Physical Peramenters