Work Profile Report [33W1071]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शासनादेश सं0 161/जि0यो0/2017-18 दिनांक 27-1-18
TS Amount (lakhs) : 8 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy :
6.20
For CFY 2024-2025
Remaining :
1.80
Demand :
1.80
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.20
Work completed
Sanction on : 6 years 9 months ago
27 Jan 2018
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 7 months ago
31 Mar 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
काय पूर्ण। भुगतान शेष। -- as on 31-Mar-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand