Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
33W1112 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 2560/।।।(2)/18-47 (प्रा0आ0) /2017 दिनांक 7 जून 2018
TS Amount (lakhs) : 9.95 Lacs
Financial Detail
Sanction Cost : 9.95 Lacs
Resanction Cost : 9.95 Lacs
Exp. Upto Last Fy : 9.16 Lacs
For CFY 2024-2025
Remaining : 0.79 Lacs
Demand : 0.79 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.16 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 11 months ago
07 Jun 2018
Tentative Completion date:
5 years 1 month ago
31 Mar 2019
Actual Completion Date:
1 month 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 03-Nov-2023
Physical Peramenters