Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.2 | 0.2 | 0.2 | 0 |
33W1114 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 3347/।।।(2)/18-08 (प्रा0आ0) /2018 टी0सी0 दिनांक 12 जुलाई 2018
TS Amount (lakhs) : 23.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
23.26
Resanction Cost :
23.26
Tentative Cost :
23.26
Exp. Upto Last Fy : 18.86
For CFY 2024-2025
Remaining : 4.40
Demand : 4.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.86
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 5 days ago
12 Jul 2018
Tentative Completion date:
4 years 3 months ago
31 Mar 2020
Actual Completion Date:
5 years 3 months ago
01 Apr 2019
Remark
Bottelneck: no issue
कार्य पूर्ण। भुगतान शेष। -- as on 31-Jul-2020
Physical Peramenters