Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.22 | 1.12 | 1.12 | 0 |
33W1171 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 906/।।।(2)/21-08 प्रा0आ0 /2018 दिनांक 30 मार्च 2021
TS Amount (lakhs) : 71.9 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
71.90
Resanction Cost :
71.90
Tentative Cost :
71.90
Exp. Upto Last Fy : 51.23
For CFY 2024-2025
Remaining : 20.67
Demand : 20.67
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 51.23
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
30 Mar 2021
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
2 years 1 month ago
28 May 2022
Remark
Bottelneck: no issue
कार्य पूर्ण भुगतान शेष। -- as on 20-Apr-2023
Physical Peramenters