Work Profile Report [33W12]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 2454/111-2 /05-07(प्रा0आ0)/05 टी0सी0 दिनांक 28-10-05 एवं शा0दे0सं0 4030/।।।(2)/17-07 (प्रा0आ0)/2005 टी0सी0 दिनांक 15 दिसम्बर 2017 द्वारा पुनरीक्षित
TS Amount (lakhs) : 698.07 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
472.00
Resanction Cost :
698.07
Tentative Cost :
472.00
Saving
226.07
Exp. Upto Last Fy :
696.07
For CFY 2025-2026
Remaining :
2.00
Demand :
0.00
Allotment :
2.00
Exp in CFY :
0.00
Total Up to Date Exp :
696.07
Work completed
Sanction on : 19 years 8 months ago
28 Oct 2005
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 3 months ago
31 Mar 2022
Actual Completion Date : 3 years 3 months ago
31 Mar 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 04-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: