Work Profile

वि0ख0 मोरी के देवजानी कुमणाई(घटटुका केदारगंगा) में 15 मी0 स्पान आर0सी0सी0 पैदल पुलिया का निर्माण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : पत्रांक 312/रा0यो0आ0/जि0यो0/2021-22

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 4.36 Lacs

Resanction Cost : 10.36 Lacs

Exp. Upto Last Fy : 2.64 Lacs

For CFY 2024-2025

Remaining : 7.72 Lacs

Demand : 7.72 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 2.64 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
2 years 9 months ago
26 Jul 2021


Tentative Completion date:
1 year 1 month ago
31 Mar 2023


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


कार्य पूर्ण। -- as on 22-Apr-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 1 0