Work Profile Report [33W1219]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 5727/III(2)/21-16(प्रा0आ0)
TS Amount (lakhs) : 76.68 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.68
Resanction Cost :
76.68
Tentative Cost :
76.68
Exp. Upto Last Fy :
72.60
For CFY 2024-2025
Remaining :
4.08
Demand :
4.08
Allotment :
4.08
Exp in CFY :
5.00
Total Up to Date Exp :
77.60
Work completed
Sanction on : 3 years 3 weeks ago
30 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 3 months ago
31 Aug 2022
Actual Completion Date : 2 years 3 months ago
13 Sep 2022
Physical Linear Components
Remark
कार्य पूर्ण भुगतान शेष। -- as on 20-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: