Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
33W1233 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 420/III(2)/21-49(प्रा0आ0)/2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
49.90
Resanction Cost :
49.90
Tentative Cost :
49.90
Exp. Upto Last Fy : 6.82
For CFY 2024-2025
Remaining : 43.08
Demand : 1.74
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.82
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
2 years 6 months ago
05 Jan 2022
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण स्वीकृत।वनभूमि प्रस्ताव गठित किया जा रहा है। -- as on 20-Apr-2023
Physical Peramenters