Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
33W1250 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 476/lll(2)/21-29(प्रा0आ0)/2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 11.48 Lacs
Resanction Cost : 11.48 Lacs
Exp. Upto Last Fy : 1.89 Lacs
For CFY 2024-2025
Remaining : 9.59 Lacs
Demand : 9.59 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.89 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 5 months ago
07 Dec 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर दिनांक 15-12-2023 को वन एवं राजस्व विभाग के साथ संयुक्त निरीक्षण किया गया तथा वन विभाग द्वारा आख्या अपेक्षित। -- as on 04-Jan-2024
Physical Peramenters