Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
33W1256 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : I/52992/2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.98
Resanction Cost :
10.98
Tentative Cost :
10.98
Exp. Upto Last Fy : 4.21
For CFY 2024-2025
Remaining : 6.77
Demand : 6.77
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 11 months ago
27 Jul 2022
Tentative Completion date:
10 months 2 weeks ago
31 Aug 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Feb-2024