Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
33W1265 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : I/59774/2022
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 169.20 Lacs
Resanction Cost : 169.20 Lacs
Exp. Upto Last Fy : 159.54 Lacs
For CFY 2024-2025
Remaining : 9.66 Lacs
Demand : 9.66 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 159.54 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 8 months ago
01 Sep 2022
Tentative Completion date:
5 months 3 weeks ago
22 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण तथा पी0सी0आर0 अधिशासी अभियंता, निर्माण खण्ड, लो0नि0वि0, पुरोला के पत्रांक 2431/13सी0 दिनांक 01-12-2023 के द्वारा अधीक्षण अभियंता, छठा वृत्त, लो0नि0वि0, उत्तरकाशी को प्रेषित। -- as on 02-Dec-2023
Physical Peramenters