Work Profile

जिला योजना वर्ष 2022-23 के अन्तर्गत खाबली गुन्दियाटगाॅव मोटर मार्ग के कि0मी0 11 से मोल्टाड़ी मन्दिर तक मोटर मार्ग।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 141/रा0यो0आ0/जि0यो0/2022-23

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 14.00 Lacs

Resanction Cost : 14.00 Lacs

Exp. Upto Last Fy : 5.37 Lacs

For CFY 2024-2025

Remaining : 8.63 Lacs

Demand : 8.63 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 5.37 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
1 year 3 months ago
24 Jan 2023


Tentative Completion date:
11 months 2 weeks ago
31 May 2023


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


कार्य पूर्ण। -- as on 05-Jun-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 1 0