Work Profile Report [33W1303]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 142/रा0यो0आ0/जि0यो0/2022-23
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
1.00
For CFY 2024-2025
Remaining :
2.00
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.00
Construction Started
Sanction on : 1 year 11 months ago
24 Jan 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
50 %
Tentative Completion date on : 1 year 2 months ago
30 Sep 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 21-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: