Work Profile Report [33W1354]

राज्य योजना के अन्तर्गत रामा रेवडी मोटर मार्ग का सुदृढीकरण व डामरीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E file no. 51197

TS Amount (lakhs) : 36.7 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

36.70

Resanction Cost :

36.70

Tentative Cost :

36.70

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

36.70

Demand :

30.70

Allotment :

34.75

Exp in CFY :

34.74

Total Up to Date Exp :

34.74

Work completed

Sanction on : 1 year 4 months ago

30 Jun 2023

Physical Progress:

At start of FY 2024-2025 :

20 %

Up to Date :

100 %

Tentative Completion date on : 5 months 3 weeks ago

31 May 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
1.25
1.25
0.000
1.25
1.250
1.250

Remark

view all

कार्य पूर्ण। -- as on 05-Nov-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: