Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 5.000 |
33W1358 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E fil e no. 49748
TS Amount (lakhs) : 349.69 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
350.08
Resanction Cost :
350.08
Tentative Cost :
350.08
Exp. Upto Last Fy : 177.78
For CFY 2024-2025
Remaining : 172.30
Demand : 172.30
Allotment : 172.30
Exp in CFY : 151.45
Total Up to Date Exp : 329.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 95 %
Sanction on :
1 year 4 days ago
13 Jul 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण। शेष प्रगति पर है। -- as on 10-May-2024
Physical Peramenters