Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 106 | 106 | 10.000 | 96 | 1.800 | 0.000 |
33W1361 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांक सं0 - 2937/III(2)/23-01(प्रा0आ0)/2019
TS Amount (lakhs) : 656.26 Lacs
Financial Detail
Sanction Cost : 656.26 Lacs
Resanction Cost : 656.26 Lacs
Exp. Upto Last Fy : 525.95 Lacs
For CFY 2024-2025
Remaining : 130.31 Lacs
Demand : 129.65 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 525.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
9 months 1 week ago
11 Aug 2023
Tentative Completion date:
10 months 21 hours from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10.00 कि0मी0 लम्बाई में क्रैश बैरियर का कार्य पूर्ण व 4000 नं0 डेलनेटर का कार्य पूर्ण।शेष कार्य प्रगति पर है। -- as on 21-Mar-2024
Physical Peramenters