Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 106 | 106 | 10.000 | 96 | 1.800 | 1.800 |
33W1361 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांक सं0 - 2937/III(2)/23-01(प्रा0आ0)/2019
TS Amount (lakhs) : 656.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
656.26
Resanction Cost :
656.26
Tentative Cost :
656.26
Exp. Upto Last Fy : 525.95
For CFY 2024-2025
Remaining : 130.31
Demand : 129.65
Allotment : 85.00
Exp in CFY : 74.72
Total Up to Date Exp : 600.67
Work completed
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 100 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
8 months 2 days from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।भुगतान शेष। -- as on 03-Jun-2024
Physical Peramenters