Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.43 | 9.43 | 0.000 | 9.43 | 0.300 | 0.300 |
33W1362 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांक सं0 - 2937/III(2)/23-01(प्रा0आ0)/2019 dated 11-08-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.90
Resanction Cost :
94.90
Tentative Cost :
94.90
Exp. Upto Last Fy : 49.98
For CFY 2024-2025
Remaining : 44.92
Demand : 44.92
Allotment : 0.00
Exp in CFY : 10.41
Total Up to Date Exp : 60.38
Work completed
Physical Progress:
At start of FY 2024-2025 : 77 %
Up to Date : 100 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
8 months 2 days from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।भुगतान शेष। -- as on 03-Jun-2024
Physical Peramenters