Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.43 | 9.43 | 0.000 | 9.43 | 0.300 | 0.000 |
33W1362 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांक सं0 - 2937/III(2)/23-01(प्रा0आ0)/2019 dated 11-08-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 94.90 Lacs
Resanction Cost : 94.90 Lacs
Exp. Upto Last Fy : 49.98 Lacs
For CFY 2024-2025
Remaining : 44.92 Lacs
Demand : 44.92 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 49.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 77 %
Up to Date : 77 %
Sanction on :
9 months 1 week ago
11 Aug 2023
Tentative Completion date:
10 months 19 hours from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
01 कि0मी0 लम्बाई में क्रैश बैरियर का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 15-Feb-2024
Physical Peramenters