Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
33W1365 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E fil e no. 48419
TS Amount (lakhs) : 169.02 Lacs
Financial Detail
Sanction Cost : 169.02 Lacs
Resanction Cost : 169.02 Lacs
Exp. Upto Last Fy : 61.27 Lacs
For CFY 2024-2025
Remaining : 107.75 Lacs
Demand : 107.75 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 56.85 Lacs
Total Up to Date Exp : 118.13 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
8 months 1 week ago
08 Sep 2023
Tentative Completion date:
3 weeks 5 days ago
23 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 04-Jan-2024
Physical Peramenters