Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
33W1365 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E fil e no. 48419
TS Amount (lakhs) : 169.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
169.02
Resanction Cost :
169.02
Tentative Cost :
169.02
Exp. Upto Last Fy : 55.77
For CFY 2024-2025
Remaining : 113.25
Demand : 107.75
Allotment : 56.89
Exp in CFY : 56.85
Total Up to Date Exp : 112.62
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
1 month 2 days from now
20 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण।शेष कार्य प्रगति पर है। -- as on 26-Jun-2024