Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.07 | 2.07 | 0.000 | 2.07 | 2.070 | 0.000 |
33W1416 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file No. 49748
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 101.55 Lacs
Resanction Cost : 101.55 Lacs
Exp. Upto Last Fy : 31.07 Lacs
For CFY 2024-2025
Remaining : 70.48 Lacs
Demand : 70.48 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.07 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 80 %
Sanction on :
5 months 1 week ago
06 Dec 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 06-Feb-2024
Physical Peramenters