Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.07 | 2.07 | 0.000 | 2.07 | 2.070 | 2.070 |
33W1416 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file No. 49748
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
101.55
Resanction Cost :
101.55
Tentative Cost :
101.55
Exp. Upto Last Fy : 31.07
For CFY 2024-2025
Remaining : 70.48
Demand : 70.48
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 31.07
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 95 %
Sanction on :
7 months 1 week ago
06 Dec 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण।शेष प्रगति पर। -- as on 26-Jun-2024
Physical Peramenters