Work Profile

जिला योजना वर्ष 2023-24 के अन्तर्गत पांव तल्ला से मोटर मार्ग तक पी0सी0सी0 कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 43/VIII-DP-07/लो0नि0वि0 (01)/जि0यो0/2023-24

TS Amount (lakhs) : 3 Lacs

Financial Detail

Sanction Cost : 3.00 Lacs

Resanction Cost : 3.00 Lacs

Exp. Upto Last Fy : 0.00 Lacs

For CFY 2024-2025

Remaining : 3.00 Lacs

Demand : 3.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 0.00 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 50 %

Up to Date : 50 %

Sanction on :
6 months 3 weeks ago
27 Oct 2023


Tentative Completion date:
2 weeks 5 days ago
30 Apr 2024


Actual Completion Date:
Not Yet Reported


Rating : 50

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 08-Dec-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 0 1 1 0
Currently only Bank Gaurantee information is avilable