Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1 | 1 | 0 |
33W16 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0दे0सं0 455(1)।।।-2/05 दि0 24-2-06
TS Amount (lakhs) : 29.4 Lacs
Financial Detail
Sanction Cost : 29.40 Lacs
Resanction Cost : 29.40 Lacs
Exp. Upto Last Fy : 10.78 Lacs
For CFY 2024-2025
Remaining : 18.62 Lacs
Demand : 3.40 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.78 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
18 years 2 months ago
24 Feb 2006
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
वर्तमान मंे कास्तकारांे का प्रतिकर भुगतान की कार्यवाही की जा रही है। -- as on 06-Oct-2023
Physical Peramenters