Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 1.000 | 4 | 4.000 | 0.000 |
33W30 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 764/111‘2‘/08-65 प्रा0आ0/07 दि0 24-3-08
TS Amount (lakhs) : 183.75 Lacs
Financial Detail
Sanction Cost : 183.75 Lacs
Resanction Cost : 183.75 Lacs
Exp. Upto Last Fy : 15.06 Lacs
For CFY 2024-2025
Remaining : 168.69 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 15.06 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 30 %
Sanction on :
16 years 1 month ago
24 Mar 2008
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
Cutting Work start -- as on 06-Mar-2024
Physical Peramenters