Work Profile

33W30 :

No Pic Avilable Time series Gantt
fमयांगाड से कुनारा लुदराला मोटर मार्ग का fनर्माण कार्य, fक0मी0 13 से 17


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 764/111‘2‘/08-65 प्रा0आ0/07 दि0 24-3-08

TS Amount (lakhs) : 183.75 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

183.75

Resanction Cost :

183.75

Tentative Cost :

183.75

Exp. Upto Last Fy : 15.06

For CFY 2024-2025

Remaining : 168.69

Demand : 100.00

Allotment : 27.00

Exp in CFY : 26.77

Total Up to Date Exp : 41.83

Construction Started

Physical Progress:

At start of FY 2024-2025 : 20 %

Up to Date : 30 %

Sanction on :
16 years 3 months ago
24 Mar 2008


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 33

Remark

Bottelneck: Other Reason


Cutting Work start -- as on 06-Mar-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 5 1.000 4 4.000 0.000
Currently only Bank Gaurantee information is avilable