Work Profile Report [33W30]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 764/111‘2‘/08-65 प्रा0आ0/07 दि0 24-3-08
TS Amount (lakhs) : 183.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
183.75
Resanction Cost :
183.75
Tentative Cost :
183.75
Exp. Upto Last Fy :
129.97
For CFY 2025-2026
Remaining :
53.78
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
129.97
Construction Started
Sanction on : 17 years 1 week ago
24 Mar 2008
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
90 %
Tentative Completion date on : 2 years 3 months from now
30 Jul 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Cutting Work start -- as on 06-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: