Work Profile Report [33W30]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 764/111‘2‘/08-65 प्रा0आ0/07 दि0 24-3-08
TS Amount (lakhs) : 183.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
183.75
Resanction Cost :
183.75
Tentative Cost :
183.75
Exp. Upto Last Fy :
15.06
For CFY 2024-2025
Remaining :
168.69
Demand :
100.00
Allotment :
85.91
Exp in CFY :
70.72
Total Up to Date Exp :
85.78
Construction Started
Sanction on : 16 years 9 months ago
24 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
80 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Cutting Work start -- as on 06-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand