Administrative Approval Detail : fजलाfधकारी उत्तरकाशी का पत्रांक 541/fज0यो0 fदनांक 10-12-12
TS Amount (lakhs) : 3 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
3.00
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Work completed
Sanction on : 12 years 2 weeks ago
10 Dec 2012
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 8 months ago
31 Mar 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 22-Apr-2023