Work Profile Report [33W45]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 3318/111(2) /06- 09 (प्रा0आ0)/06 टी0सी0-1 दि0 12-12-06
TS Amount (lakhs) : 81.48 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.48
Resanction Cost :
81.48
Tentative Cost :
81.48
Exp. Upto Last Fy :
74.33
For CFY 2025-2026
Remaining :
7.15
Demand :
7.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
74.33
Work completed
Sanction on : 18 years 3 months ago
12 Dec 2006
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on : 6 days 54 minutes ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण भुगतान शेष। -- as on 07-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: