Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
33W481 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी उत्तरकाशी का पत्रांक 477/fज0यो0 -ओ0एम0डी0/2013 fदनांक 23-9-13
TS Amount (lakhs) : 2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2.00
Resanction Cost :
2.00
Tentative Cost :
2.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 2.00
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 9 months ago
23 Sep 2013
Tentative Completion date:
10 years 3 months ago
31 Mar 2014
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 31-Jul-2020
Physical Peramenters