Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 8 | 8 | 8 | 0 |
33W851 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी उत्तरकाशी का पत्रांक 592/fज0यो0 fदनांक 26-2-2015
TS Amount (lakhs) : 5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy : 2.86
For CFY 2024-2025
Remaining : 2.14
Demand : 2.14
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.86
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 4 months ago
26 Feb 2015
Tentative Completion date:
8 years 3 months ago
31 Mar 2016
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। भुगतान शेष। -- as on 30-Apr-2021
Physical Peramenters