Work Profile Report [33W863]

fजला योजना वर्ष 2015-16 के अन्तर्गत ग्राम अराकोट के पीछे सम्पर्क मार्ग fनर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : fजलाfधकारी उत्तरकाशी का पत्रांक 106/fज0यो0 fदनांक 7-12-2015

TS Amount (lakhs) : 9 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

9.00

Resanction Cost :

9.00

Tentative Cost :

9.00

Exp. Upto Last Fy :

5.99

For CFY 2024-2025

Remaining :

3.01

Demand :

3.01

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

5.99

Work completed

Sanction on : 8 years 11 months ago

07 Dec 2015

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 6 years 7 months ago

31 Mar 2018

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
0.5
0.5
0.5
-

Remark

view all

कार्य पूर्ण। -- as on 31-Jul-2020

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand