Work Profile Report [33W929]

नैटवाड़ से दोणी (मान्चा) तक मोटर मार्ग का डामरीकरण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 4203/।।।(2)/15-05 (मा0मु0घो0)/ 2015 दिनांक 16-2-2016

TS Amount (lakhs) : 237.08 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

237.08

Resanction Cost :

237.08

Tentative Cost :

237.08

Exp. Upto Last Fy :

225.31

For CFY 2024-2025

Remaining :

11.77

Demand :

11.77

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

225.31

Work completed

Sanction on : 8 years 10 months ago

16 Feb 2016

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 years 8 months ago

31 Mar 2020

Actual Completion Date : 5 years 2 months ago

01 Oct 2019

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

कार्य पूर्ण। भुगतान शेष। -- as on 31-Jul-2020

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand