Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.02 | 5.02 | 0.000 | 5.02 | 5.000 | 0.000 |
34W1001 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 ई-फाइल 46119 लो0नि0वि0 अनुभाग-2 देहरादून दि0 23.03.2023
TS Amount (lakhs) : 468.59 Lacs
Financial Detail
Sanction Cost : 468.59 Lacs
Resanction Cost : 468.59 Lacs
Exp. Upto Last Fy : 159.00 Lacs
For CFY 2024-2025
Remaining : 309.59 Lacs
Demand : 200.00 Lacs
Allotment : 70.28 Lacs
Exp in CFY : 5.34 Lacs
Total Up to Date Exp : 164.35 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 1 month ago
23 Mar 2023
Tentative Completion date:
6 months 3 days from now
23 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3 km hill cutting, 2 km part 2 and soiling complete. work in progress. -- as on 23-Mar-2024