Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
34W1003 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 31503 लो0नि0वि0 अनुभाग-2 देहरादून दि0 28.03.2023
TS Amount (lakhs) : 206.82 Lacs
Financial Detail
Sanction Cost : 206.82 Lacs
Resanction Cost : 206.82 Lacs
Exp. Upto Last Fy : 116.49 Lacs
For CFY 2024-2025
Remaining : 90.33 Lacs
Demand : 90.32 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 26.61 Lacs
Total Up to Date Exp : 143.11 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 1 month ago
28 Mar 2023
Tentative Completion date:
1 month 5 days from now
25 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
PC work starting. -- as on 10-May-2024
Physical Peramenters