Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
34W1014 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल संख्या- 38540.00 दिनांक 30.06.2023
TS Amount (lakhs) : 261.62 Lacs
Financial Detail
Sanction Cost : 261.62 Lacs
Resanction Cost : 261.62 Lacs
Exp. Upto Last Fy : 187.45 Lacs
For CFY 2024-2025
Remaining : 74.17 Lacs
Demand : 74.16 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 187.45 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
10 months 2 weeks ago
30 Jun 2023
Tentative Completion date:
4 months 3 days from now
23 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
PC work started. -- as on 10-May-2024
Physical Peramenters