Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
34W1018 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No- 38540
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 73.37 Lacs
Resanction Cost : 73.37 Lacs
Exp. Upto Last Fy : 49.09 Lacs
For CFY 2024-2025
Remaining : 24.28 Lacs
Demand : 23.64 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 3.17 Lacs
Total Up to Date Exp : 52.26 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
7 months 3 weeks ago
26 Sep 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
hill side cutting work in progress. -- as on 18-Feb-2024
Physical Peramenters