Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
34W1018 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No- 38540
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
73.37
Resanction Cost :
73.37
Tentative Cost :
73.37
Exp. Upto Last Fy : 49.09
For CFY 2024-2025
Remaining : 24.28
Demand : 23.64
Allotment : 4.00
Exp in CFY : 6.17
Total Up to Date Exp : 55.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 90 %
Sanction on :
9 months 3 weeks ago
26 Sep 2023
Tentative Completion date:
2 weeks 5 hours ago
03 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Hill side cutting work completed. -- as on 03-Jun-2024
Physical Peramenters