Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
34W1022 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 ई-फाईल ंन0- 38540 लो0नि0वि0 अनुभाग-2 देहरादून दि0 26.09.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 2.90
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
9 months 3 weeks ago
26 Sep 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
survey work complete. -- as on 12-Jul-2024