Work Profile Report [34W1067]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 ई-फाईल ंन0- 68883 लोक निर्माण अनुभाग-2 देहरादून दि0 06.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.50
Resanction Cost :
7.50
Tentative Cost :
7.50
Exp. Upto Last Fy :
2.75
For CFY 2025-2026
Remaining :
4.75
Demand :
4.75
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.75
Survey work done
Sanction on : 1 year 1 month ago
06 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 4 weeks 14 hours ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
survey work complete. -- as on 14-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand