Work Profile Report [34W1068]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई-फाईल संख्या- 70105 लोक निर्माण अनुभाग-2 देहरादून दि0 15.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
82.59
Resanction Cost :
82.59
Tentative Cost :
82.59
Exp. Upto Last Fy :
81.31
For CFY 2025-2026
Remaining :
1.28
Demand :
1.28
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
81.31
Construction Started
Sanction on : 1 year 1 month ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 4 weeks 14 hours ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
90% कार्य पूर्ण। जी0एस0बी0,जी 2, जी 3, इण्टरलाकिंग कार्य पूर्ण। स्कपर कार्य प्रगति पर। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: