Work Profile Report [34W1069]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाईल न0-55022 & शासनादेश संख्या-359/XXXVI(2)/24/12-बजट/2023 न्याय अनुभाग-2 उत्तराखण्ड शासन देहरादून दि0 15.03.2024
TS Amount (lakhs) : 172.76 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
184.83
Resanction Cost :
184.83
Tentative Cost :
184.83
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
184.83
Demand :
65.00
Allotment :
65.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 9 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 10 months 6 days from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
site development work complete. -- as on 10-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand