Work Profile Report [34W1080]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 ई-फाईल ंन0- 75874 लो0नि0वि0 अनुभाग-2 देहरादून दि0 05.09.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
13.23
Resanction Cost :
13.23
Tentative Cost :
13.23
Exp. Upto Last Fy :
4.09
For CFY 2025-2026
Remaining :
9.14
Demand :
9.14
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.09
Survey work done
Sanction on : 7 months 3 weeks ago
05 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधीक्षण अभियन्ता 6वां वृत्त लो0नि0वि0 उत्तरकाशी के पत्रांक 1131/51-6/2024-25 दिनांक 04/04/2025 द्वारा स्थल चयन प्रस्ताव अनुमोदित। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: