Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 9.5 | 9.5 | 0 |
34W14 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 830/111-2 /06-29 प्रा0आ0/07 दिनांक 24.03.08
TS Amount (lakhs) : 341.12 Lacs
Financial Detail
Sanction Cost : 296.88 Lacs
Resanction Cost : 296.88 Lacs
Exp. Upto Last Fy : 220.69 Lacs
For CFY 2024-2025
Remaining : 76.19 Lacs
Demand : 76.20 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 220.69 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
16 years 1 month ago
24 Mar 2008
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
scupper and walling work in progress. -- as on 01-Mar-2024
Physical Peramenters